How a Self-Erect Concrete Paving Plant became a 3 Day set-up.
March 10, 2012Colorado Concrete Paving Contractor incorporates a CON-E-CO 427CM Portable Paving Plant to meet quick set-up requirements. Installation criteria by the contractor was the use of only a boom truck and 988 loader. The single stage hydraulic rams allow the contractor to erect the concrete paving plant in only a few days. The material feed conveyors are quickly converted from transportation to operation mode with only a few field changes. The 2 compartment in-truss frame silo is fed by cement pigs or guppy’s. Mixer clearance for be adjusted for a end-dump truck or a concrete mixer truck. Plant production is approximately 320 yards per hour.